Trending Today ...
Bullhead City gears up for Spring sports season

BULLHEAD CITY – The City of Bullhead City

Temporary road closure required at Smoketree Ave for

LAKE HAVASU CITY – Lake Havasu City Public

City working with ASU to seek input on

KINGMAN – The City of Kingman’s Economic Development and

Mardi Gras Dueling Piano Soirée

KINGMAN – Join an unforgettable evening of mystery

Sacrifice

Whether one agrees with the new presidential administration

Poker run to benefit patient transportation

LAKE HAVASU CITY – Local healthcare nonprofit Don't

Thank you for reading The Standard newspaper online!

Kingman completes Devlin sewer project

KINGMAN – The completion of the New Kingman-Butler Sewer Expansion Project marks an important milestone for the county. With the allocation of American Rescue Plan Act (ARPA) funds by the Board of Supervisors in 2021, District 4 residents can now benefit from improved infrastructure in the area for years to come.

The project allocated $2.5 million to the design and construction of the Devlin Sewer line, providing sewer availability to over 200 parcels and expansion opportunity to over 2,700 parcels. An Intergovernmental Agreement with the City of Kingman outlined responsibilities of each entity during the design, construction, inspection and acceptance of the Devlin Sewer line.

The City of Kingman approved the construction to be completed in three phases. When construction began, letters were sent to property owners in the project area to take advantage of discounted connection costs. Of over 200 letters sent, 88 took advantage of the discounted rate and were connected. The city is also waiving the Sewer Investment Fee and/or Wastewater Capacity Fee for properties that connect within one year of acceptance of each phase.

Premier Backhoe Inc. will finish construction, final paving, and septic abandonments by January 31.