Trending Today ...
Letter to the Editor
Hey Keith, it’s only bye for now

Dear Editor, My longtime buddy Keith passed away

barbecue
Friends of Mohave County Animal Shelter Customer Appreciation

To our amazing community, In order to find

New Star Trek-Themed magic set draws crowd to

KINGMAN, Ariz. – A new Magic: The Gathering

scam
City of Kingman warns public about fraudulent emails

Kingman, AZ - The City of Kingman is warning

radar hill
Annual Radar Hill Tree Lighting

KINGMAN, Ariz. – Kingman Chamber of Commerce and

fundraiser
Fundraiser to benefit senior center

KINGMAN, Ariz – A benefit fundraiser will be

Thank you for reading The Standard newspaper online!

Decision made on Flying Fortress water drainage

Kingman City Council chambers

KINGMAN, Ariz. – Kingman City Council met in a special session Tuesday night, Oct. 27, to vote on which option of water drainage system to approve to finish the Flying Fortress interchange.

Option A was the one they had initially intended to go with. It involved creating 15 cascading water basins, occupying 6.8 acres of land near the road and neighboring houses and would have needed additional fencing. 

Option B was a new option being considered. A landowner offered to donate land to the city to create one large basin 20- to 25-feet deep just off I-40.

It was determined that both sites were in a flood zone. Option A would be a temporary fix for the city, while Option B would be a more permanent one with a cost savings of over $1 million.

The council voted to approve Option B, which would need no fencing because “it’s in the middle of nowhere,” according to City Engineer Mike Garmon.

The project is expected to be completed by mid-January 2027.

Connie “Ceejay” Jones