The citizens of Mohave County can expect the following road maintenance activity during the week of August 10:
Arizona Strip: Road grading on Mount Trumbull Loop.
Kingman: Road grading on 1) Falcon Valley Rd., 2) Calle Puebla and 3) Calle Ocampo. Crews will be crack sealing on Thompson Ave. They will be repairing the right of way and repairing pot holes in the Butler area.
Hackberry: Road grading on Antares Rd. working south.
Wikieup: Road grading on Signal Rd.
Yucca: Road grading on 1) Alamo Rd. from Mile 40 to Mile 52, 2) Alamo Rd. from Mile 7 to end of pavement, 3) Planet Ranch Rd. and 4) Whispering Winds Dr.
Hualapai Mtn. Area: Road grading in the Lazy Y U area.
Golden Valley: Road grading on SE: 1) Hassayampa Rd. from Redwall Dr. to Abrigo Dr. and 2) Shipp Dr. from San Pedro Rd. to Teddy Roosevelt Rd. S: 1) Navajo Dr. from Garnet Rd. to Gold Road Trl. and 2) Signal Rd. from Navajo Dr. to end of maintenance. SW: 1) Bolsa Dr. from Estrella Rd. to Laguna Rd., 2) Canelo Rd. from Bolsa Dr. to end of maintenance and 3) Cordes Rd. from Bolsa Dr. to Diabase Dr. NE: 1) Canelo Rd. from Agua Fria Dr. to Zuni Dr. and 2) Cibola Rd. from Agua Fria Dr. to Simon Dr. NW: 1) Egar Dr. from Agua Fria Dr. to Chinle Dr. and 2) Chinle Dr. from Egar Dr. to Dilkon Rd.
White Hills: Road grading on 1) Fairway Dr. from White Hills Rd. to end of maintenance and 2) Rolling Ridge Dr. from Fairway Dr. to White Fox Dr.
Dolan Springs: Road grading on 1) Twentieth St. from Pellet Dr. to Olive Dr., 2) Pellet Dr. from Nineteenth St. to Twentyfirst St. and 2) Palo Alto Dr. from Nineteenth St. to Pierce Ferry Rd.
Meadview: Road grading on 1) Crescent Dr., 2) Boathouse Dr. 3) Detrital Dr., 4) Cathedral Dr. and 5) Middle Point Dr. from Mead Dr. to Sandy Point Dr.
Mohave Valley: Repairing pot holes on Oatman Hwy. and clearing drivers’ line of sight on Oatman Hwy. from Mile 1 to Mile 2. Repairing drainage ditch on Boundary Cone Rd., mowing road shoulders in the Perry Acres area and street sweeping in the Sun Valley area of Fort Mohave.
Lake Havasu: Pulling road shoulders on London Bridge Rd.
Heavy Road Maintenance Projects:
Pierce Ferry Rd. Widening — July 2020 through November 5, 2020 — Paving eastbound widened section and non-motorized trail to
Mt. Tipton School.
Vanderslice Rd. / From the MCSO substation for one mile north (North of Reservation Rd.) — June 8 through August 16 — CEMEX: One mile of concrete pavement.
El Rodeo Rd. / Hwy 95 to Mountain View Rd. and Mountain View Rd. / El Rodeo Rd. to Joy Ln. — September 8 through 11 — Cactus Asphalt: Placing rubberized chip seal.